AIDC 101.

Many workstreams. One opening day.

Illustrative schedule · One campus phase · Months since project start
Month 5.0
Rotatable three-dimensional data center construction model. The schedule below provides the same readiness information.
Drag to rotate · Watch the campus rise
Parallel workOpening-date constraints (including ties)Vertical line = playback month
0816

Learning experiment

If the transformer arrives three months earlier, how much earlier can the campus open?

This is a teaching model, not a construction forecast. Fixed assumptions: site access in month 6; building and distribution ready in month 8; compute and network ready in month 9; one month for transformer installation and one month for integrated testing. Capacity ramp, procurement eligibility, demand and revenue are outside this model.