The megawatt had a deadline. A planned 23,000-GPU supercomputer at Loughton carried a Q1 2027 customer window. The reported grid-power horizon moved into the early-to-mid 2030s. Microsoft withdrew. That is more than a delay. A megawatt arriving after the customer's planning window can be a different product. AI capacity is not just a GPU count or a power number. It is power, place and time arriving together. The useful sequence is: announced → contracted → powered → commissioned → revenue-producing. Each arrow needs its own evidence. A signature does not energize a rack. Full story and sources: https://iamrobin.ai/binary/stories/the-megawatt-had-a-deadline/ #AIInfrastructure #DataCenters #PowerGrid #Commissioning #SystemsThinking